Section 327IAC15-13-11. Compliance schedule  


Latest version.
  •    An MS4 operator shall comply with the following schedule for implementation of this rule:

    Rule Requirement

    Compliance Deadline

    (from initial NOI letter receivership date)

    Storm Water Quality Management Plan:

    Components throughout term of permit

    Part A: Initial Application submitted

    With NOI letter

    Part B: Baseline Characterization and Report submitted

    180 days

    Part C: Program Implementation submitted

    1 year

    Public Education and Outreach MCM implementation:

    Throughout term of permit

    Public education and outreach program development certification submitted

    1 year

    Public Involvement/Participation MCM implementation:

    Throughout term of permit

    Public involvement and participation program development certification submitted

    1 year

    Illicit Discharge Detection/Elimination MCM implementation:

    Throughout term of permit

    Illicit discharge plan and regulatory mechanism certification submitted

    1 year

    25% of storm water outfalls systems mapped

    Each year after 1 year

    All known storm water outfall systems, with pipe diameters 12 inches or greater or open ditches with 2 feet or larger bottom width, mapped

    5 years

    Construction Site Run-Off Control MCM implementation:

    Throughout term of permit

    Construction site program plan and regulatory mechanism certification submitted

    1 year

    Postconstruction Run-Off Control MCM implementation:

    Throughout term of permit

    Operational and maintenance plan certification submitted

    2 years

    Postconstruction program plan and regulatory mechanism certification submitted

    2 years

    Municipal operations pollution prevention and good housekeeping MCM implementation:

    Throughout term of permit

    Operations pollution prevention program development certification submitted

    1 year

    If an MS4 operator is unable to meet a compliance deadline under this section the operator shall submit a written request and justification for extending the deadline. The request must be submitted to the department no later than thirty (30) days prior to the due date. (Water Pollution Control Division; 327 IAC 15-13-11; filed Jul 7, 2003, 2:15 p.m.: 26 IR 3587)