Indiana Administrative Code (Last Updated: December 20, 2016) |
Title 327. WATER POLLUTION CONTROL DIVISION |
Article 327IAC15. NPDES GENERAL PERMIT RULE PROGRAM |
Rule 327IAC15-13. Storm Water Run-Off Associated with Municipal Separate Storm Sewer System Conveyances |
Section 327IAC15-13-11. Compliance schedule
-
An MS4 operator shall comply with the following schedule for implementation of this rule:
Rule Requirement
Compliance Deadline
(from initial NOI letter receivership date)
Storm Water Quality Management Plan:
Components throughout term of permit
Part A: Initial Application submitted
With NOI letter
Part B: Baseline Characterization and Report submitted
180 days
Part C: Program Implementation submitted
1 year
Public Education and Outreach MCM implementation:
Throughout term of permit
Public education and outreach program development certification submitted
1 year
Public Involvement/Participation MCM implementation:
Throughout term of permit
Public involvement and participation program development certification submitted
1 year
Illicit Discharge Detection/Elimination MCM implementation:
Throughout term of permit
Illicit discharge plan and regulatory mechanism certification submitted
1 year
25% of storm water outfalls systems mapped
Each year after 1 year
All known storm water outfall systems, with pipe diameters 12 inches or greater or open ditches with 2 feet or larger bottom width, mapped
5 years
Construction Site Run-Off Control MCM implementation:
Throughout term of permit
Construction site program plan and regulatory mechanism certification submitted
1 year
Postconstruction Run-Off Control MCM implementation:
Throughout term of permit
Operational and maintenance plan certification submitted
2 years
Postconstruction program plan and regulatory mechanism certification submitted
2 years
Municipal operations pollution prevention and good housekeeping MCM implementation:
Throughout term of permit
Operations pollution prevention program development certification submitted
1 year
If an MS4 operator is unable to meet a compliance deadline under this section the operator shall submit a written request and justification for extending the deadline. The request must be submitted to the department no later than thirty (30) days prior to the due date. (Water Pollution Control Division; 327 IAC 15-13-11; filed Jul 7, 2003, 2:15 p.m.: 26 IR 3587)