Section 327IAC15-3-3. Deadline for submittal of an NOI letter; additional requirements
-
(a) Any person proposing a new discharge that will be subject to a general permit under 327 IAC 15-6, 327 IAC 15-7, or 327 IAC 15-14 shall submit an NOI letter and additional information as required by the applicable general permit rule at least one hundred eighty (180) days before the date on which the discharge is to commence unless permission for a later date has been granted by the commissioner or is established in the applicable general permit rule.
(b) For construction activity under 327 IAC 15-5-5, a construction activity NOI letter shall be submitted in accordance with 327 IAC 15-5-6.
(c) For municipal separate storm sewer system discharges under 327 IAC 15-13, a municipal separate storm sewer system NOI letter shall be submitted in accordance with 327 IAC 15-13-6 and 327 IAC 15-13-9. (Water Pollution Control Division; 327 IAC 15-3-3; filed Aug 31, 1992, 5:00 p.m.: 16 IR 19; errata filed Sep 10, 1992, 12:00 p.m.: 16 IR 65; errata, 16 IR 898; readopted filed Jan 10, 2001, 3:23 p.m.: 24 IR 1518; filed Oct 27, 2003, 10:15 a.m.: 27 IR 832; readopted filed Nov 21, 2007, 1:16 p.m.: 20071219-IR-327070553BFA; readopted filed Jul 29, 2013, 9:21 a.m.: 20130828-IR-327130176BFA; filed Oct 9, 2015, 4:07 p.m.: 20151104-IR-327100659FRA; errata filed Dec 30, 2015, 12:37 p.m.: 20160113-IR-327150453ACA)