(a) The executive director, or upon recommendation by the commission, may require each contractor to submit a good and sufficient bid bond with the bid. The bid bond may equal any percentage of the estimated cost of the commission works project that the executive director requires.
(b) The consulting engineer may accept bids provided on forms specified by the commission or on forms given by surety companies. (State Fair Commission; 80 IAC 2-7-5; filed Nov 27, 1991, 2:00 p.m.: 15 IR 453; readopted filed Sep 11, 2001, 2:45 p.m.: 25 IR 528; readopted filed Oct 4, 2007, 10:29 a.m.: 20071024-IR-080070451RFA; readopted filed Sep 18, 2013, 2:12 p.m.: 20131016-IR-080130242RFA)