Section 80IAC2-7-4. Payment of subcontractors and suppliers by contractor or escrow agent; certification of previous payments  


Latest version.
  •    (a) Within ten (10) days of receipt of any payment by the commission or its designated representative, or the escrow agent, the contractor or escrow agent shall pay each subcontractor the appropriate share of the payment the contractor received based upon the service performed by the subcontractor.

      (b) The contractor shall furnish to the commission a sworn statement or certification at the time of payment to it that all subcontractors have received their share of the previous payment to the contractor. The making of an incorrect certification may be considered a breach of contract by the commission, and the commission may exercise all its rights set out in the contract in addition to the remedies for falsifying an affidavit. Making an incorrect certification may also result in a submission of notice of such falsification to the state of Indiana, public works certification board, which may result in a revocation of the contractor's qualifications under IC 4-13.6-4-13(b) at the discretion of the public works certification board. (State Fair Commission; 80 IAC 2-7-4; filed Nov 27, 1991, 2:00 p.m.: 15 IR 453; readopted filed Sep 11, 2001, 2:45 p.m.: 25 IR 528; readopted filed Oct 4, 2007, 10:29 a.m.: 20071024-IR-080070451RFA; readopted filed Sep 18, 2013, 2:12 p.m.: 20131016-IR-080130242RFA)