Indiana Administrative Code (Last Updated: December 20, 2016) |
Title 80. STATE FAIR COMMISSION |
Article 80IAC9. COMMISSION WORKS |
Rule 80IAC9-4. Bidding Requirements |
Section 80IAC9-4-9. Commencement of warranty period
Latest version.
-
Each commission works contract must require that all warranty periods applying to work performed under the contract commence not later than the date that all work under the contract is substantially completed as determined by the commission. (State Fair Commission; 80 IAC 9-4-9; filed Nov 7, 2016, 3:46 p.m.: 20161207-IR-080160210FRA)