"Construction quality control" or "CQC" means a planned system of inspections that is used to directly monitor and control the quality of a construction project. Construction quality control is normally performed by the geosynthetics manufacturer or installer, or for natural soil materials by the earthwork contractor, and is necessary to achieve quality in the constructed or installed system. Construction quality control refers to measures taken by the installer or contractor to determine compliance with the requirements for materials and workmanship as stated in the approved construction plan. (Solid Waste Management Division; 329 IAC 10-2-39; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1768)