Indiana Administrative Code (Last Updated: December 20, 2016) |
Title 327. WATER POLLUTION CONTROL DIVISION |
Article 327IAC15. NPDES GENERAL PERMIT RULE PROGRAM |
Rule 327IAC15-13. Storm Water Run-Off Associated with Municipal Separate Storm Sewer System Conveyances |
Section 327IAC15-13-6. Notice of intent letter requirements
-
(a) Unless one (1) application is submitted for multiple MS4 entities, each MS4 entity shall submit an NOI letter with the following information, which will serve as the permit application:
(1) Contact information required under subsection (b).
(2) List of all known receiving waters or, if the discharge is to another MS4, the name of the MS4 entity and the initial receiving water. For the purposes of the NOI letter submittal, receiving waters include, at a minimum, waters listed on the United States Geological Survey National Hydrography Dataset or, if no waters are listed on this data base within a given MS4 area, the primary receiving water for the MS4 area drainage. As additional receiving waters are identified, the information must be provided in the corresponding annual report required in section 18 of this rule.
(3) Copy of the completed SWQMP-Part A: Initial Application certification submittal and checklist form.
(4) Proof of publication in the newspaper with the greatest circulation in the affected MS4 area. The notice must provide a listing of all entities intended to be covered under the permit. This statement must be included in the public notice, "(MS4 entity name and address) intends to discharge storm water into the (text name and numeric code of all 14-digit Hydrologic Unit Code area) watershed(s), and is submitting a Notice of Intent letter to notify the Indiana Department of Environmental Management of our intent to comply with the requirements under 327 IAC 15-13 to discharge storm water run-off associated with municipal separate storm sewer systems.".
(5) Certification, by completing and signing Appendix A of the NOI letter, that any applicable, legally binding agreements between MS4 area entities have been obtained concerning individual responsibilities for implementation of this rule.
(b) The contact information required under subsections (a)(1) and (c)(1) must include the following:
(1) Name of MS4 operator, primary contact individual (if different from the MS4 operator), or responsible individual for each MS4 entity.
(2) Title of the MS4 operator, primary contact individual (if different from the MS4 operator), or responsible individual or individuals.
(3) MS4 entity represented by the MS4 operator, primary contact individual (if different from the MS4 operator), or responsible individual or individuals.
(4) Mailing (and, if different, the physical) address of the MS4 operator, primary contact individual (if different from the MS4 operator), or responsible individual or individuals.
(5) Telephone and facsimile number of the MS4 operator, primary contact individual (if different from the MS4 operator), or responsible individual or individuals.
(6) E-mail address (if available) of MS4 operator, primary contact individual (if different from the MS4 operator), or responsible individual or individuals.
(c) The SWQMP-Part A: Initial Application required under subsection (a)(3) must contain the following:
(1) Written listing of the MS4 entities within an MS4 area covered by the NOI letter submittal. The listing must provide the name of each MS4 entity, a responsible individual for each MS4 entity, and contact information for each MS4 entity.
(2) Written schedule which, at a minimum, adheres to the compliance schedule in section 11 of this rule.
(3) Written proposed or estimated budget allocation for the MS4 area's storm water program with a summary of identified funding sources. When multiple MS4 entities are applying under a single NOI letter, the budget allocation must be, at a minimum, separated by MS4 entity.
(d) Multiple MS4 entities within an MS4 area may submit a single NOI letter provided they comply with the submittal requirements of this section. Coverage under a single NOI letter will only be allowed if all the MS4 entities seeking coverage consolidate, and provide, the required information in sections 7, 8, and 18 of this rule as single submittals, and the information is submitted to the department by the MS4 operator designated in subsection (b). MS4 operators may utilize materials from existing local or state programs, or partner with an existing individual MS4 permittee, if all parties agree to coordinate responsibilities in accordance with subsection (a)(5).
(e) Multiple MS4 entities within an MS4 area may submit a separate NOI letter corresponding to each entity and still share responsibilities for implementation of one (1) or more of the requirements in this rule provided they comply with the submittal requirements of this section and coordinate responsibilities in accordance with subsection (a)(5).
(f) Where multiple MS4 entities submit one (1) or more NOI letters based on a watershed delineation and the created MS4 area contains undesignated MS4 entities, the undesignated MS4 entities shall not be subject to the provisions of this rule unless the applicability requirements of section 3 of this rule apply.
(g) Where the MS4 operator changes, or where a new operator is added after the submittal of an NOI letter, a new NOI letter must be completed and submitted in accordance with 327 IAC 15-2-8 and sections 6 and 9 of this rule. If no other conditions change except for the name of the MS4 operator, a written letter describing the name change and a statement that no other conditions, including those conditions in the SWQMP-Part A: Initial Application and legal agreements, have changed will be sufficient notification to the department.
(h) An MS4 entity within an MS4 area that does not have the legal authority or other regulatory mechanisms to implement one (1) or more of the six (6) minimum control measures required under this rule shall either obtain the legal authority or other regulatory mechanism, or work with a neighboring regulated MS4 entity, via legally binding agreements, to share responsibilities.
(i) All documents and information required by this section must meet the signatory requirements of 327 IAC 15-4-3(g).
(j) A qualified professional and the MS4 operator shall certify, with the stated paragraph found in 327 IAC 15-4-3(g)(3), a submitted SWQMP-Part A: Initial Application checklist form.
(k) The department shall review initially submitted NOI letters and SWQMP-Part A: Initial Applications for adequacy and shall assign each NOI letter an NPDES permit number. Either a written NOD letter requesting additional information or NOS letter containing the assigned NPDES permit number shall be returned to the MS4 operator within ninety (90) days of the NOI letter submittal. If the MS4 operator does not receive either a NOD letter or NOS letter within ninety (90) days of the NOI letter submittal, the NOI letter and SWQMP-Part A: Initial Application will be considered adequate.
(l) Responses to NOD letters shall be made by the recipient within thirty (30) days of the date on the NOD letter.
(m) Forms for the NOI letter, SWQMP, annual report, and required certifications shall be provided by the department. (Water Pollution Control Division; 327 IAC 15-13-6; filed Jul 7, 2003, 2:15 p.m.: 26 IR 3583; errata filed Sep 8, 2003, 3:15 p.m.: 27 IR 191)