Section 326IAC2-8-5. Compliance requirements for FESOPs  


Latest version.
  •    (a) Each FESOP shall contain the following requirements:

    (1) Compliance certification, testing, monitoring, reporting, and record keeping requirements sufficient to assure compliance with the terms and conditions of the FESOP. Any document (including reports) required by a FESOP shall contain a certification by an authorized individual that meets the requirements of section 3(d) of this rule. Compliance certification requirements shall include the following:

    (A) The frequency of submissions of compliance certifications.

    (B) In accordance with section 4(3) of this rule, a means for monitoring the compliance of the source with its emissions limitations, standards, and work practices.

    (C) A requirement that the compliance certification include the following:

    (i) The identification of each term or condition of the FESOP that is the basis of the certification.

    (ii) The compliance status.

    (iii) Whether compliance was continuous or intermittent.

    (iv) The methods used for determining the compliance status of the source, currently and over the reporting period.

    (v) Such other facts as the commissioner may require to determine the compliance status of the source.

    (D) Such additional requirements as may be specified under Sections 114(a)(3) and 504(b) of the CAA.

    (2) Inspection and entry requirements that require that, upon presentation of credentials and other documents as may be required by law, the permittee shall allow the commissioner, an authorized representative, or the U.S. EPA to perform the following:

    (A) Enter upon the permittee's premises where a FESOP source is located or emissions related activity is conducted, or where records must be kept under the conditions of a FESOP.

    (B) Have access to and copy, at reasonable times, any records that must be kept under the conditions of a FESOP.

    (C) Inspect, at reasonable times, any facilities, equipment (including monitoring and air pollution control equipment), practices, or operations regulated or required under a FESOP.

    (D) Sample or monitor, at reasonable times, substances or parameters for the purpose of assuring compliance with a FESOP or applicable requirements.

    (3) A schedule for compliance with any requirement with which the source is not in compliance at the time of permit issuance. Such a schedule shall include a schedule of remedial measures, including an enforceable sequence of actions with milestones leading to compliance with any requirements for which the source will be in noncompliance at the time of FESOP issuance. This compliance schedule shall resemble and be at least as stringent as that contained in any judicial consent decree or administrative order to which the source is subject. Any such schedule of compliance shall be supplemental to, and shall not sanction noncompliance with, the applicable requirements on which it is based.

    (4) Such other provisions as the commissioner may require.

      (b) The commissioner may issue a compliance order to any source upon discovery that an issued permit is in nonconformance with an applicable requirement. The order may require immediate compliance or contain a schedule for expeditious compliance with the applicable requirement. (Air Pollution Control Division; 326 IAC 2-8-5; filed May 25, 1994, 11:00 a.m.: 17 IR 2274; filed Nov 25, 1998, 12:13 p.m.: 22 IR 1053)