  •    Each owner or operator of a demolition or renovation activity to whom this section applies shall do the following:

    (1) Provide the department with written notice of the intention to demolish or renovate on a form to be provided by the department and update such notice as necessary, including, but not limited to, the following:

    (A) When the amount of affected RACM increases or decreases by at least twenty percent (20%).

    (B) If there is a change in the following:

    (i) Asbestos removal or demolition start date.

    (ii) Removal or demolition contractor.

    (iii) Waste disposal site.

    (2) Postmark or deliver the notice as follows:

    (A) At least ten (10) working days before asbestos stripping or removal work or any other activity, such as site preparation, begins that would break up, dislodge, or similarly disturb asbestos material if the operation is a demolition operation described in section 1(a) of this rule and the facility contains at least three (3) square feet, three (3) linear feet, or seventy-five hundredths (0.75) cubic foot of RACM on or off facility components.

    (B) At least ten (10) working days before demolition begins if the operation is a demolition operation described in section 1(a) of this rule and the facility contains less than three (3) square feet, three (3) linear feet, or seventy-five hundredths (0.75) cubic foot of RACM, on or off facility components, or there is no asbestos in the facility.

    (C) As early as possible before demolition begins if the operation is an ordered demolition operation described in section 1(b) of this rule.

    (D) At least ten (10) working days before asbestos stripping or removal work or any other activity, such as site preparation, begins that would break up, dislodge, or similarly disturb asbestos material, begins if the operation is a renovation operation described in section 1(c) of this rule.

    (E) As early as possible before asbestos stripping or removal work begins, but not later than the following working day, if the operation is an emergency renovation operation described in section 1(d) of this rule.

    (F) At least ten (10) working days before the end of the calendar year preceding the year for which notice is being given for planned renovation operations involving individual, nonscheduled operations described in section 1(e) of this rule.

    (G) Delivery of the notice by the U.S. Postal Service, commercial delivery service, or hand delivery is acceptable. A copy of the previous notification being revised shall be attached to the new, revised notification.

    (H) In the case of a revised notice, a copy of the original notice shall be attached.

    (3) Include the following information in the notice:

    (A) An indication of whether the notice is the original, a revised, or cancelled copy, if applicable.

    (B) Name, address, and telephone number of both the facility owner and operator, the asbestos removal contractor owner or operator, and the demolition contractor owner or operator.

    (C) Type of operation:

    (i) demolition;

    (ii) demolition by intentional burning;

    (iii) ordered demolition;

    (iv) renovation;

    (v) emergency renovation; or

    (vi) planned nonscheduled renovation (annual notice).

    (D) Description of the facility or affected part of the facility, including the size in square feet, number of floors, age, and present and prior use of the facility.

    (E) Procedure, including analytical methods, employed to detect the presence and amount of RACM and Category I and Category II nonfriable ACM.

    (F) Estimate of the approximate amount of RACM to be removed in the facility in terms of linear feet of pipe, square feet on other facility components, total cubic feet on all facility components, or total amount on or off all facility components where the length or area could not be measured previously. Also estimate the approximate amount of Category I and Category II nonfriable ACM in the affected part of the facility that will not be removed before demolition.

    (G) Location and street address, including building number or name and floor or room number, if appropriate, city, county, and state of the facility being demolished or renovated.

    (H) Scheduled starting and completion dates of asbestos removal project, as defined in section 2(7) of this rule, such as site preparation, that would break up, dislodge, or similarly disturb RACM in a demolition or renovation. Planned renovation operations involving individual, nonscheduled operations shall only include the beginning and ending dates of the report period as described in section 1(e) of this rule.

    (I) For renovation operations, scheduled starting and completion dates of the renovation project.

    (J) For demolition operations, scheduled starting and completion dates of the actual facility demolition.

    (K) Description of planned demolition or renovation work to be performed and methods to be employed, including demolition or renovation techniques to be used and a description of the affected facility components.

    (L) Description of work practices and engineering controls to be used to comply with this rule, including RACM removal and waste handling emission control procedures.

    (M) Description of procedures to be followed in the event that unexpected RACM is found or Category I or Category II nonfriable ACM becomes crumbled, pulverized, or reduced to powder.

    (N) Name and location of the waste disposal site where the asbestos-containing waste material will be deposited.

    (O) A signed certification from the owner or operator that at least one (1) person trained as required by 40 CFR 61.145, paragraph (c)(8)* will supervise the stripping and removal described by this notification.

    (P) A signed certification from the owner or operator that the information provided in this notification is correct and that only Indiana licensed workers and project supervisors will be used to implement the asbestos removal project.

    (Q) For facilities described in section 1(b) of this rule, the name, title, and authority of the state or local governmental representative who has ordered the demolition, the date that the order was issued, and the date on which the demolition was ordered to begin. A copy of the order shall be attached to the notification.

    (R) For demolition and renovation projects described in section 1(a) through 1(e) of this rule, include the name, address, telephone number, and license number issued under 326 IAC 18 of the following:

    (i) Person who inspected the facility for RACM.

    (ii) Person who designed the asbestos removal project if RACM is present, if applicable.

    (iii) Person who will implement the asbestos removal project if RACM is present.

    (S) For emergency renovations described in section 1(d) of this rule, the date and hour that the emergency occurred, a description of the sudden, unexpected event, and an explanation of how the event caused an unsafe condition or would cause equipment damage.

    (T) Name, address, and telephone number of the waste transporter.

    (4) When the stripping or removal of RACM in demolition or renovation operations described in section 1(a) and 1(c) of this rule will begin:

    (A) on a date after the date specified in the original or the most recent revised notification, provide written notice of the new stripping or removal start date to the department postmarked at least five (5) working days or delivered at least two (2) working days before the start date of asbestos stripping or removal specified in the notification that is being revised; or

    (B) on a date earlier than the date specified in the original or the most recent revised notification, provide written notice of the new stripping or removal start date to the department postmarked or delivered at least ten (10) working days before the start date of asbestos stripping or removal work begins.

    (5) When the demolition described in section 1(a) of this rule, including the demolition of facilities with no asbestos, will begin on a date later than the date specified in the original or the most recent revised notification, written notice of the new demolition start date must be provided to the department postmarked at least:

    (A) five (5) working days; or

    (B) delivered at least two (2) working days;

    before the start date of demolition specified in the notification that is being revised.

    (6) When the demolition described in section 1(a) of this rule, including the demolition of facilities with no asbestos, will begin on a date earlier than the date specified in the original or the most recent revised notification, written notice of the new demolition start date must be provided to the department postmarked at least ten (10) working days before the start date of demolition.

    (7) In no event shall RACM removal work (or any other activity, including site preparation that would break up, dislodge, or similarly disturb asbestos material) or demolition activities begin on a date other than the date contained in the most recent written notification.

      *This document is incorporated by reference. Copies may be obtained from the Government Printing Office, 732 North Capitol Street NW, Washington, D.C. 20401 or are available for review and copying at the Indiana Department of Environmental Management, Office of Air Quality, Indiana Government Center-North, Tenth Floor, 100 North Senate Avenue, Indianapolis, Indiana 46204. (Air Pollution Control Division; 326 IAC 14-10-3; filed Dec 5, 1990, 3:40 p.m.: 14 IR 610; filed Mar 28, 1995, 2:00 p.m.: 18 IR 2016; errata filed Apr 12, 1995, 3:30 p.m.: 18 IR 2261; filed May 12, 1998, 9:15 a.m.: 21 IR 3743; errata filed Dec 12, 2002, 3:35 p.m.: 26 IR 1571; filed Aug 26, 2004, 11:30 a.m.: 28 IR 91)