Terms used in this rule not defined in this section are defined as set forth in 40 CFR 61, Subpart A*. The following definitions apply throughout this rule:
(1) "Active waste disposal site" means any disposal site other than an inactive site.
(2) "Adequately wet" means to sufficiently mix or penetrate with liquid to prevent the release of particulates. If visible emissions are observed coming from RACM, then that material has not been adequately wetted. However, the absence of visible emissions is not sufficient evidence of being adequately wet.
(3) "Asbestos" means an asbestiform variety of the following:
(A) Chrysotile (serpentine).
(B) Crocidolite (ribeckite).
(C) Amosite (cummingtonite-grunerite).
(D) Anthophyllite.
(E) Tremolite.
(F) Actinolite.
(4) "Asbestos-containing waste materials" means any waste that contains commercial asbestos and is generated by a source subject to the provisions of this article. This term includes filters from control devices, friable asbestos waste material, and bags or other similar packaging contaminated with commercial asbestos. As applied to demolition and renovation operations, this term includes RACM waste and materials contaminated with asbestos, including disposable equipment and clothing.
(5) "Asbestos-containing material" or "ACM" means asbestos or any material containing more than one percent (1%) asbestos as determined using methods specified in 40 CFR 763, Subpart E, Appendix E, Section I, Polarized Light Microscopy*, including Category I and Category II asbestos-containing material and all friable material.
(6) "Asbestos mill" means any facility engaged in converting, or in any intermediate step in converting, asbestos ore into commercial asbestos. Outside storage of asbestos material is not considered a part of the asbestos mill.
(7) "Asbestos removal project" means any and all activities at a facility involving the removal, encapsulation, enclosure, abatement, renovation, storage, stripping, dislodging, cutting, or drilling that result in the disturbance or repair of any one (1) of the following:
(A) At least three (3) linear feet of RACM on or off pipes.
(B) At least three (3) square feet of RACM on or off other facility components.
(C) A total of at least seventy-five hundredths (0.75) cubic foot of RACM on or off all facility components.
These activities include, but are not limited to, work area preparation, implementation of engineering controls and work practices, and work area decontamination activities required by section 4 of this rule or 29 CFR 1926.1101*.
(8) "Asbestos tailings" means any solid waste that contains asbestos and is a product of asbestos mining or milling operations.
(9) "Asbestos waste from control devices" means any waste material that contains asbestos and is collected by a pollution control device.
(10) "Category I nonfriable asbestos-containing material (ACM)" means asbestos-containing packings, gaskets, resilient floor covering, and asphalt roofing products containing more than one percent (1%) asbestos as determined using the method specified in 40 CFR 763, Subpart E, Appendix E, Section 1, Polarized Light Microscopy*.
(11) "Category II nonfriable asbestos-containing material (ACM)" means any material, excluding Category I nonfriable ACM, containing more than one percent (1%) asbestos as determined using the method specified in 40 CFR 763, Subpart E, Appendix E, Section 1, Polarized Light Microscopy* that, when dry, cannot be crumbled, pulverized, or reduced to powder by either hand pressure or mechanical forces reasonably expected to act on the material.
(12) "Commercial asbestos" means any material containing asbestos that is extracted from ore and has value because of its asbestos content.
(13) "Cutting" means to penetrate with a sharp-edged instrument and includes sawing, but does not include shearing, slicing, or punching.
(14) "Demolition" means the wrecking or taking out of any load-supporting structural member of a facility together with any related handling operations or the intentional burning of any facility.
(15) "Emergency renovation operation" means a renovation or operation that was not planned but results from a sudden, unexpected event that, if not immediately attended to, presents a safety or public health hazard or is necessary to protect equipment from damage. This term includes operations necessitated by nonroutine failures of equipment.
(16) "Facility" means any:
(A) school building;
(B) institutional, commercial, public, or industrial building or residential structure, installation, or building (including any structure, installation, or building containing condominiums or individual dwelling units operated as a residential cooperative, but excluding residential buildings having four (4) or fewer dwelling units);
(C) ship; and
(D) active or inactive waste disposal site.
For purposes of this definition, any building, structure, or installation that contains a loft used as a dwelling is not considered a residential structure, installation, or building. Any structure, installation, or building that was previously subject to this article is included regardless of its current use or function.
(17) "Facility component" means any part of a facility, including equipment.
(18) "Friable asbestos material" means any material containing more than one percent (1%) asbestos as determined using the method specified in 40 CFR 763, Subpart E, Appendix E, Section 1, Polarized Light Microscopy*, that, when dry, can be crumbled, pulverized, or reduced to powder either by hand pressure or mechanical forces reasonably expected to act on the material. If the asbestos content is less than ten percent (10%) as determined by a method other than point counting by polarized light microscopy (PLM), verify the asbestos content by point counting using PLM.
(19) "Fugitive source" means any source of emissions not controlled by an air pollution control device.
(20) "Glove bag" means a sealed compartment with attached inner gloves used for the handling of ACM. Properly installed and used, glove bags provide a small work area enclosure typically used for small scale asbestos stripping operations. Information on glove bag installation, equipment and supplies, and work practices is contained in the Occupational Safety and Health Administration's (OSHA) final rule on occupational exposure to asbestos (Appendix G to 29 CFR 1926.1101*).
(21) "Grinding" means to reduce to powder or small fragments and includes mechanical chipping or drilling.
(22) "HEPA filter" means a high efficiency particulate air filter capable of trapping and retaining at least ninety-nine and ninety-seven hundredths percent (99.97%) of all monodispersed particles of three-tenths (0.3) micrometers in diameter or larger.
(23) "In poor condition" means the binding of the material is losing its integrity as indicated by peeling, cracking, or crumbling of the material.
(24) "Inactive waste disposal site" means any disposal site or portion of it where additional asbestos-containing waste material has not been deposited within the previous twelve (12) months.
(25) "Installation" means any building or structure or any group of buildings or structures at a single demolition or renovation site that are under the control of the same owner or operator (or owner or operator under common control), including, but not limited to, a group of residential buildings being demolished as part of an urban renewal project or highway project.
(26) "Leak-tight" means that solids or liquids cannot escape or spill out. It also means dust-tight.
(27) "Malfunction" means any sudden and unavoidable failure of air pollution control equipment or process equipment or of a process to operate in a normal or usual manner so that emissions of asbestos are increased. Failures of equipment shall not be considered malfunctions if they are caused in any way by poor maintenance, careless operation, or any other preventable upset conditions, equipment breakdown, or process failure.
(28) "Manufacturing" means the combining of commercial asbestos or, in the case of woven friction products, the combining of textiles containing commercial asbestos with any other materials, including commercial asbestos, and the processing of this combination into a product. Chlorine production is considered a part of manufacturing.
(29) "Nonfriable asbestos-containing material" means any material containing more than one percent (1%) asbestos as determined using the method specified in 40 CFR 763, Subpart E, Appendix E, Section 1, Polarized Light Microscopy*, that, when dry, cannot be crumbled, pulverized, or reduced to powder by either hand pressure or mechanical forces reasonably expected to act on the material.
(30) "Nonscheduled renovation operation" means a renovation operation necessitated by the routine failure of equipment, which is expected to occur within a given period based on past operating experience, but for which an exact date cannot be predicted.
(31) "Ordered demolition" means demolition of a facility under an order of a state or local governmental agency, issued because the facility is both structurally unsound and in danger of imminent collapse.
(32) "Outside air" means the air outside buildings and structures, including, but not limited to, the air under a bridge or in an open air ferry dock.
(33) "Owner or operator of a demolition or renovation activity" means any person who owns, leases, operates, controls, or supervises the facility being demolished or renovated or any person who owns, leases, operates, controls, or supervises the demolition or renovation operation, or both.
(34) "Particulate asbestos material" means finely divided particles of asbestos or material containing asbestos.
(35) "Planned renovation operations" means a renovation operation, or a number of such operations, in which some RACM will be removed or stripped within a given period of time and that can be predicted. Individual, nonscheduled operations are included if a number of such operations can be predicted to occur during a given period of time based on operating experience.
(36) "Regulated asbestos-containing material (RACM)" means the following:
(A) Friable asbestos material.
(B) Category I nonfriable ACM that has become friable.
(C) Category I nonfriable ACM that will be or has been subjected to sanding, grinding, cutting, abrading, or burning.
(D) Category II nonfriable ACM that has a high probability of becoming or has become crumbled, pulverized, or reduced to powder by the forces expected to act on the material in the course of demolition or renovation operations regulated by this article.
The term does not include nonfriable asbestos-containing resilient floor covering materials unless the materials are sanded, beadblasted, or mechanically pulverized so that visible asbestos emissions are discharged or the materials are burned. Resilient floor covering materials, including sheet vinyl flooring, resilient tile, and associated adhesives.
(37) "Remove" means to take out RACM or facility components that contain or are covered with RACM from any facility.
(38) "Renovation" means altering a facility or one (1) or more facility components in any way, including the stripping or removal of RACM from a facility component together with any related handling operation. Operations in which load-supporting structural members are wrecked or taken out are demolitions.
(39) "Resilient floor covering" means asbestos-containing floor tile, including asphalt and vinyl floor tile, and sheet vinyl floor covering containing more than one percent (1%) asbestos as determined using polarized light microscopy according to the method specified in 40 CFR 763, Subpart E, Appendix E, Section 1, Polarized Light Microscopy*.
(40) "Roadways" means surfaces on which vehicles travel. The term includes, among other surfaces, public and private highways, roads, streets, parking areas, and driveways.
(41) "Sanitary landfill" has the meaning set forth in 329 IAC 10-2-116.
(42) "School" means any combination of grades kindergarten, 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, or 12.
(43) "School building" means the following:
(A) Any structure at a school suitable for use as a classroom, laboratory, library, school eating facility, or facility used for the preparation of food.
(B) Any gymnasium or other facility at a school that is specifically designed for athletic or recreational activities for an academic course in physical education.
(C) Any other facility used by a school for the instruction or housing of students or for the administration of educational or research programs.
(D) Any maintenance, storage, or utility facility, including any hallway, essential to the operation of any facility described in clauses (A) through (C).
(E) Any portico or covered exterior hallway or walkway that is part of a school.
(F) Any exterior portion of a mechanical system used to heat, ventilate, or air condition (HVAC) the interior space of a school.
(44) "Strip" means to take off RACM from any part of a facility or facility components.
(45) "Structural member" means any load-supporting member of a facility, such as beams and load-supporting walls, or any nonload-supporting member, such as ceilings and nonload-supporting walls.
(46) "Visible emissions" means any emissions, which are visually detectable without the aid of instruments, emitted from RACM or asbestos-containing waste material, or from any asbestos milling, manufacturing, or fabricating operation. This does not include condensed uncombined water vapor.
(47) "Waste generator" means any owner or operator of a source covered by this article whose act or process produces asbestos-containing waste material.
(48) "Waste shipment record" means the shipping document, required to be originated and signed by the waste generator, used to track and substantiate the disposition of asbestos-containing waste material.
(49) "Work area" means the facility, room, or portion of a facility or room where an asbestos removal project is about to occur, is in progress, or has been completed, extending to the point where access to the area, as indicated by either the plastic or poly which forms and surrounds the containment area, or demarcation by sign(s) or barrier tape, including, but not limited to, the glove bag operation area, is limited to those workers or supervisors, or other persons authorized by the employer and required by work duties to be present in regulated areas, implementing the asbestos removal project.
(50) "Working day" means Monday through Friday and includes holidays that fall on any of the days Monday through Friday.
*These documents are incorporated by reference. Copies may be obtained from the Government Printing Office, 732 North Capitol Street NW, Washington, D.C. 20401 or are available for review and copying at the Indiana Department of Environmental Management, Office of Air Quality, Indiana Government Center-North, Tenth Floor, 100 North Senate Avenue, Indianapolis, Indiana 46204. (Air Pollution Control Division; 326 IAC 14-10-2; filed Dec 5, 1990, 3:40 p.m.: 14 IR 609; filed Mar 28, 1995, 2:00 p.m.: 18 IR 2013; filed May 12, 1998, 9:15 a.m.: 21 IR 3740; errata filed Dec 12, 2002, 3:35 p.m.: 26 IR 1571; filed Aug 26, 2004, 11:30 a.m.: 28 IR 88)