Section 326IAC26-1-8. Part 70 permit modifications


Latest version.
  •    (a) Within five (5) years of the effective date of this rule, the Part 70 permit of a source subject to BART that is required to submit a BART analysis shall be reopened and modified in accordance with 326 IAC 2-7-9 to reflect all approved BART requirements or alternatives to the BART requirements to include the following:

    (1) Enforceable emission limits, if applicable.

    (2) Design, equipment, work practice, operation standard, or combination of these types of standards, if applicable.

    (3) Compliance schedules that require compliance with the requirements in subdivisions (1) and (2) within five (5) years of the effective date of this rule.

      (b) Enforceable emission limits and compliance schedules that reflect the BART requirements or an approved alternative to the BART requirements shall be included in the Part 70 permit in accordance with the following:

    (1) 40 CFR 51, Appendix Y, "Guidelines for BART Determinations Under the Regional Haze Rule*".

    (2) 40 CFR 51.308(e)*, "Best Available Retrofit Technology (BART) requirements for regional haze visibility impairment".

    (3) 326 IAC 2-7.

      (c) The requirements listed in subsection (a) shall be submitted to U.S. EPA for approval into the state implementation plan.

      *These documents are incorporated by reference. Copies may be obtained from the Government Printing Office, 732 North Capitol Street NW, Washington, D.C. 20401 or are available for review and copying at the Indiana Department of Environmental Management, Office of Air Quality, Indiana Government Center-North, Tenth Floor, 100 North Senate Avenue, Indianapolis, Indiana 46204. (Air Pollution Control Division; 326 IAC 26-1-8; filed Jan 23, 2008, 1:37 p.m.: 20080220-IR-326060208FRA)