Section 25IAC9-4-1. Monitoring IVBE participation  


Latest version.
  •    (a) The department may conduct preproposal meetings with prime and subcontractors. The department shall determine which projects will require a preproposal meeting. Items of discussion at the meetings may include, but are not limited to, the following:

    (1) A review of program requirements.

    (2) Subcontractor services.

      (b) All change orders, amendments, and other modifications to the contract that affect value must include an explanation of the following:

    (1) How IVBE will be utilized.

    (2) Any IVBE percentage changes to the original contract amount.

      (c) IVBE primes shall receive credit toward the contract goal for the use of its own workforce. (Indiana Department of Administration; 25 IAC 9-4-1; filed Feb 28, 2014, 8:05 a.m.: 20140326-IR-025130402FRA)