Section 80IAC2-1-15. "Substantial completion" defined  


Latest version.
  •    "Substantial completion" means the condition of a commission work when it is sufficiently completed, in accordance with the contract documents as modified by any completed change orders agreed to by the parties, so that the commission can occupy or take possession of the commission work and use it as it is intended to be used. (State Fair Commission; 80 IAC 2-1-15; filed Nov 27, 1991, 2:00 p.m.: 15 IR 446; readopted filed Sep 11, 2001, 2:45 p.m.: 25 IR 528; readopted filed Oct 4, 2007, 10:29 a.m.: 20071024-IR-080070451RFA; readopted filed Sep 18, 2013, 2:12 p.m.: 20131016-IR-080130242RFA)