Section 329IAC11-12-2. Preoperational requirements


Latest version.
  •    Before beginning operation, a solid waste processing facility must complete the initial facility development outlined in the permitted plans and specifications. Initial facility development includes the following:

    (1) Construction of buildings or structures and on-site roads.

    (2) Installation of equipment for storage, processing, and handling of solid waste.

    (3) Installation of the following:

    (A) Access control.

    (B) Sanitary facilities.

    (C) Signs.

    (D) Communication devices.

    (E) Utilities.

    (4) Financial assurance must be established under 329 IAC 11-16 for the solid waste processing facility.

    (Solid Waste Management Division; 329 IAC 11-12-2; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1941; readopted filed Jan 10, 2001, 3:25 p.m.: 24 IR 1535; readopted filed May 14, 2007, 1:53 p.m.: 20070523-IR-329070138BFA; filed Jun 28, 2010, 2:11 p.m.: 20100728-IR-329060070FRA; readopted filed Jun 6, 2016, 11:52 a.m.: 20160706-IR-329160144BFA.1)