Rule 329IAC11-12. Solid Waste Processing Facilities; Operation Approval and Preoperational Requirements |
Section 329IAC11-12-2. Preoperational requirements
-
Before beginning operation, a solid waste processing facility must complete the initial facility development outlined in the permitted plans and specifications. Initial facility development includes the following:
(1) Construction of buildings or structures and on-site roads.
(2) Installation of equipment for storage, processing, and handling of solid waste.
(3) Installation of the following:
(A) Access control.
(B) Sanitary facilities.
(C) Signs.
(D) Communication devices.
(E) Utilities.
(4) Financial assurance must be established under 329 IAC 11-16 for the solid waste processing facility.
(Solid Waste Management Division; 329 IAC 11-12-2; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1941; readopted filed Jan 10, 2001, 3:25 p.m.: 24 IR 1535; readopted filed May 14, 2007, 1:53 p.m.: 20070523-IR-329070138BFA; filed Jun 28, 2010, 2:11 p.m.: 20100728-IR-329060070FRA; readopted filed Jun 6, 2016, 11:52 a.m.: 20160706-IR-329160144BFA.1)