Section 329IAC10-39-4. Multiple facilities  


Latest version.
  •    A permittee may use a single financial responsibility mechanism to meet the requirements for more than one (1) solid waste land disposal facility. Evidence of financial responsibility submitted to the commissioner must include a list showing, for each solid waste land disposal facility, the following:

    (1) The solid waste land disposal facility permit number, name, and address.

    (2) The amount of funds available through the mechanism that must be no less than the sum of funds that would be available if a separate mechanism had been established and maintained for each solid waste land disposal facility.

    (Solid Waste Management Division; 329 IAC 10-39-4; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1923; filed Aug 2, 1999, 11:50 a.m.: 22 IR 3872)