Section 329IAC8-5-2. Acceptance of the grant  


Latest version.
  •    Upon acceptance of the grant, the following applies:

    (1) The department shall pay the grantee seventy-five percent (75%) of the grant for the project on acceptance.

    (2) The remaining twenty-five percent (25%) of the grant shall be paid to the grantee after the grantee submits the following to the department:

    (A) Final report of the program.

    (B) Final expenditures have been audited and approved in writing from the department.

    (Solid Waste Management Division; 329 IAC 8-5-2; filed Aug 27, 1992, 9:00 a.m.: 16 IR 34; readopted filed Jan 10, 2001, 3:25 p.m.: 24 IR 1535; readopted filed May 14, 2007, 1:53 p.m.: 20070523-IR-329070138BFA; readopted filed Jul 29, 2013, 9:20 a.m.: 20130828-IR-329130179BFA)