Section 327IAC5-21-3. Permit application submission requirements  


Latest version.
  •    An application for an IWP permit must conform to the following:

    (1) Be completed on a form prescribed by the commissioner.

    (2) Be signed in accordance with 327 IAC 5-2-22(a).

    (3) Be submitted to the commissioner according to the following time requirements:

    (A) No later than one hundred eighty (180) days prior to the expiration date of an existing permit if the industrial user intends to continue discharging to the POTW.

    (B) No later than one hundred eighty (180) days prior to the date when a new industrial discharger intends to commence discharging to a POTW.

    (C) In the case of an initial issuance of an IWP permit to a significant industrial user or to an industrial user determined by the commissioner to be subject to the IWP permit requirements, no later than one hundred twenty (120) days after the latter of:

    (i) the promulgation of an applicable categorical pretreatment standard; or

    (ii) the date of notification by the commissioner of a determination made according to section 2(a)(2) of this rule.

    (D) No later than one hundred twenty (120) days prior to a planned expansion or modification of production or treatment facilities or processes that are likely to cause a significant increase in quantity of pollutants or a change in the nature of pollutants discharged to the POTW by an industrial user with an existing IWP permit.

    (Water Pollution Control Division; 327 IAC 5-21-3; filed Oct 10, 2000, 3:02 p.m.: 24 IR 315)