Section 326IAC2-7-14. Temporary source permits  


Latest version.
  •    The commissioner may issue a single Part 70 permit authorizing emissions from similar operations by the same source owner or operator at multiple temporary locations. The operation must be temporary and involve at least one (1) change of location during the term of a Part 70 permit. No affected source shall be permitted as a temporary source. Part 70 permits for temporary sources shall include the following:

    (1) Conditions that will assure compliance with all applicable requirements at all authorized locations.

    (2) Requirements that the owner or operator notify the commissioner at least ten (10) days in advance of each change in location.

    (3) Conditions that assure compliance with all other provisions of sections 5 through 7, 13, 15, and 16 of this rule.

    (Air Pollution Control Division; 326 IAC 2-7-14; filed May 25, 1994, 11:00 a.m.: 17 IR 2264)