Section 312IAC25-4-121. Review, public participation, and approval or disapproval of permit applications; permit terms and conditions; mine maps  


Latest version.
  •    All operations in existence prior to July 29, 1982, that seek approval of a permit under the requirements of IC 14-34 shall be required to submit to the director an accurate map of the mine and permit area at a scale of 1:6000 or larger. The map shall show, as of the effective date of the permanent regulatory program permit, the lands from which coal has not yet been removed and the lands and structures that have been used or disturbed to facilitate mining as of that date. This map shall be submitted to the director within sixty (60) days after the effective date of such permit. (Natural Resources Commission; 312 IAC 25-4-121; filed Jun 21, 2001, 2:53 p.m.: 24 IR 3492, eff Dec 1, 2001; readopted filed May 29, 2007, 9:51 a.m.: 20070613-IR-312070146RFA; readopted filed Sep 19, 2013, 10:12 a.m.: 20131016-IR-312130125RFA)