Section 312IAC10-4-1. License requirement for construction in a floodway
Latest version.
-
(a) Except as otherwise provided in IC 14-28-1 or this article, a license from the department is required to erect, make, use, maintain, suffer, or permit a structure, obstruction, deposit, or excavation in or on a floodway.
(b) Notwithstanding subsection (a), a person must not erect an abode in a floodway, except as authorized under IC 14-28-1-24, IC 14-28-1-25, and IC 14-28-1-26.5. (Natural Resources Commission; 312 IAC 10-4-1; filed Jul 5, 2001, 9:12 a.m.: 24 IR 3392, eff Jan 1, 2002; readopted filed Jul 21, 2008, 12:00 p.m.: 20080813-IR-312080072RFA; readopted filed Sep 22, 2014, 12:34 p.m.: 20141022-IR-312140065RFA)