Section 25IAC2-5-4. Exception from bidding; emergency work  


Latest version.
  •    The commissioner may authorize contracts to perform necessary work or construction in an emergency as described in 25 IAC 2-11 without calling for bids under normal procedures. Authorization for such emergency work will be given verbally by the commissioner or the director if so delegated. In either case, the award shall be confirmed in writing with copies filed with the department as provided under 25 IAC 2-11. (Indiana Department of Administration; Public Works Division Sec E,4; filed Feb 29, 1972,4:10 p.m.: Rules and Regs. 1973, p.4; filed Feb 3, 1982, 1:05 p.m.: 5 IR 512; readopted filed Nov 20, 2001, 9:30 a.m.: 25 IR 1265; filed Nov 14, 2007, 11:10 a.m.: 20071212-IR-025060515FRA; readopted filed Oct 18, 2013, 1:38 p.m.: 20131113-IR-025130403RFA)