Section 170IAC4-6-16. Ratemaking treatment; preconstruction costs of clean coal technology  


Latest version.
  •    A utility that engages in one (1) or more clean coal technology projects may classify preconstruction costs related to the projects as operating expenses and record these expenses in a deferred account. The utility may seek ratemaking treatment of the preconstruction costs in a general rate case before the commission. If the utility classifies preconstruction costs as operating expenses, the utility shall not record the same amounts as CWIP. (Indiana Utility Regulatory Commission; 170 IAC 4-6-16; filed Oct 5, 1993, 5:00 p.m.: 17 IR 180; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA; readopted filed Aug 2, 2013, 2:16 p.m.: 20130828-IR-170130227RFA)