Section 170IAC4-4.1-13. Reporting requirements for proposed alternate energy production and cogeneration facilities  


Latest version.
  •    (a) "Facility" for purposes of this section means any alternate energy production and cogeneration facility as previously defined under 170 IAC 4-4.1-1.

      (b) Persons wishing to proceed with the construction of a facility as defined for purposes of this section, will submit a report to the commission entailing the following:

    (1) the location of the facility;

    (2) the form(s) of energy output of the facility;

    (3) the owner(s), form and percentage of ownership of the facility;

    (4) the maximum electric generating capacity of the facility;

    (5) the expected annual electric energy output of the facility for the first five years of its operation;

    (6) the primary fuel to be used for the production of electricity by the facility; and

    (7) the expected life of the facility; and

    (8) the expected date of commercial operation for the facility.

      This report will be submitted to the commission at least one year prior to the commencement of the proposed construction of the facility. (Indiana Utility Regulatory Commission; 170 IAC 4-4.1-13; filed Mar 7, 1985, 10:04 am: 8 IR 766; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA; readopted filed Aug 2, 2013, 2:16 p.m.: 20130828-IR-170130227RFA)